Tom Breur
5 January 2014
Agile, and also Lean, carries the notion of “deciding at the
last responsible moment.” To be clear, this is a metaphor, there is no such
thing as a discrete moment in time where the cost of delaying the decision any
further goes up by some step function.
Many of these ideas were criticized by (among others) Alistair Cockburn
in his post “Last
Responsible Moment reconsidered.” Another concern is that you never know
when that “last responsible moment” is, until it is too late.
Maassen and Matts wrote an interesting graphic novel “Commitment” where they make the case
that you should never commit early
unless you know why. And most of those reasons, arguably, align nicely with the
original notion of “deciding at the last responsible moment.” It also aligns
with the Lean concept of “Just-in-Time.”
Don’t do work (too) early, because while it sits around waiting, it represents
waste. Not good.
The practical challenge in knowledge work, of course, is that
there are usually multiple decisions that need to be made. And they happen more
or less in parallel. The more complex the system will be, the more decisions
you need to make. They will likely have some interdependencies, too. And more
often than not, it is all but obvious what that ‘true’ “last responsible
moment” was.
There is uncertainty and variation in systems. You ‘plan’
(schedule) some work (regardless of whether ‘formal’ estimates
were made), and sometimes things don’t go according to plan. The more
sequential dependencies you have, the more likely it is that one (or more) component might get
delayed. Such are the “laws” of mathematics.
If somewhere along the value stream you are waiting for
upstream decisions that haven’t been made, this is just as wasteful as having
work waiting for downstream processing. Both contribute to Work-in-Progress.
Which constitutes waste and additional liability. Eli Goldratt’s book “The
Goal” provides excellent background into this. David
Anderson’s book looks at this phenomenon specifically for Software
Engineering.
If you take note of dependencies, and remain aware of
variation in your system, I still feel you can gain by delaying decisions.
Maybe not “as late as possible”, but at least later, if you can. The main reasons for this are twofold. First, you
defer investments, which gives a higher economic return for your project. More
importantly, you will have gained more knowledge, allowing you to make a better decision.